The range most sources quote for an office fit out in Dubai is wide enough to be almost useless without context. The difference between AED 60 and AED 1,200 per square foot is not randomness; it is the gap between a basic functional workspace on a finished Cat A floor and a fully branded premium fit-out from shell-and-core. This guide breaks down what each grade costs, what moves the number, and what should be in every quote before you agree to anything.
What does an office fit out cost in Dubai?
According to Emirian, typical 2026 ranges for office fit out in Dubai are: Cat A (shell to basic usable standard) AED 150 to 350 per sq ft; Cat B (standard fit to occupancy with partitions, joinery, MEP and finishes) AED 350 to 700 per sq ft; premium or turnkey AED 700 to 1,200+ per sq ft.
These are fit-out construction costs. Approval fees, design drawings, furniture and AV systems are separate budget items.
What is the difference between Cat A and Cat B fit out?
Cat A brings a shell-and-core space to a basic lettable condition: raised floors or screeded concrete, suspended ceilings, standard lighting, essential MEP and blank walls. The result is functional but not ready for a team to occupy; it is the standard a landlord delivers to a commercial tenant at lease start.
Cat B is the tenant fit-out from that point: partitions, meeting rooms, reception, branded joinery, flooring finishes, AV, lighting and workstations. According to A5renova (Aug 2026), Cat B on a finished Cat A base runs AED 60 to 120 per sq ft for a basic functional fit-out, AED 120 to 250 for mid-range corporate standard, and AED 250 to 450+ for high-end or bespoke. If you are taking shell-and-core space rather than a Cat A floor, budget for both layers.
What factors drive the cost of an office fit out in Dubai?
| Factor | Cost impact | Example |
|---|---|---|
| Fit-out grade | 8x spread across basic to premium Cat B | AED 60 to AED 450+ per sq ft |
| Starting base | Shell-and-core adds Cat A cost before Cat B starts | Adds AED 150 to 350 per sq ft on top |
| Location | +20 to 25% in DIFC, Downtown and Business Bay vs JLT | Same spec costs more in a premium address |
| MEP complexity | Higher in older or non-free-zone buildings | Chilled water changeover; dual-authority submissions |
| Approvals | AED 5,000 to 25,000 for drawings and permit fees | Fit out in a free zone adds authority-specific submissions |
Emirian notes that offices in DIFC, Downtown Dubai and Business Bay cost 20 to 25 percent more than the same specification in JLT or Dubai Internet City, before any difference in fit-out scope.
How much does a 1,000 sq ft office fit out cost in Dubai?
For a standard mid-range Cat B fit-out on a finished Cat A floor, 1,000 sq ft at AED 120 to 250 per sq ft totals AED 120,000 to 250,000 before approvals and furniture. A premium Cat B fit-out at AED 350 to 700 per sq ft would run AED 350,000 to 700,000 for the same floor area. Starting from shell-and-core adds the Cat A layer.
On a recent project we completed at 4,713 sq ft, the client came in expecting a lower total. Their estimate was based on an assumed floor area that turned out to be short of the actual size. When we completed the site measurement, the confirmed figure came in higher and the final cost followed. What they had not anticipated was simply that the floor area was larger than they had assumed. Our commitment is always to the per-square-foot rate, not the total. Once the measurement was confirmed, the revised figure was straightforward and the client accepted it.
Approval fees and design drawings typically add AED 5,000 to 25,000 depending on the authority and the complexity of the MEP and fire safety submissions.
How long does an office fit out in Dubai take?
A straightforward Cat B fit-out runs approximately 4 to 10 weeks from design sign-off to handover, according to A5renova (Aug 2026): design 1 to 3 weeks, authority approvals 1 to 3 weeks, construction and MEP 3 to 8 weeks, testing and handover 1 to 2 weeks.
Larger or more complex fits take longer. For a full breakdown by scope and common reasons for delay, see our guide on how long an office fit out takes in Dubai.
Why do office fit out budgets in Dubai go over?
The most common reason is a quote that left line items out of scope. A contractor who wins on price often wins by exclusion: approval fees, furniture, AV systems and project management are absent from the initial number and reappear as variations once you are committed. We see this in every market segment.
The second reason is materials. A quote that says “quality finishes” rather than naming specific products by brand, grade and thickness gives the contractor room to substitute after sign-off. If the contract does not specify the materials, there is no breach when cheaper alternatives arrive on site. Attach a materials schedule before you sign: every product named, every grade and thickness stated, any deviation subject to written approval before work proceeds.
When should you use a project management company for an office fit out?
A project management company does not reduce the cost of the work. It reduces the cost of the surprises.
The fit-out contractor builds; the PMC specifies the scope and materials upfront, supervises on site, holds the contractor to the schedule and enforces the materials schedule on the client’s behalf. That matters most when the business cannot afford delay or when coordinating multiple trades, fit-out permits and Civil Defence approvals across a large floor would otherwise fall to someone who already has a full-time role.
Frequently asked questions
How much does an office fit out cost per sq ft in Dubai?+
According to Emirian, typical 2026 ranges are AED 150 to 350 per sq ft for Cat A, AED 350 to 700 for Cat B and AED 700 to 1,200+ for premium or turnkey. Approval fees, design drawings, furniture and AV systems are separate budget items.
What is the difference between Cat A and Cat B fit out?+
Cat A brings a shell-and-core space to a basic lettable condition: ceilings, standard lighting, essential MEP and blank walls. Cat B is the tenant fit out from that point: partitions, meeting rooms, reception, joinery, flooring finishes, AV, lighting and workstations.
How long does an office fit out take in Dubai?+
A straightforward Cat B fit out runs approximately 4 to 10 weeks from design sign-off to handover, according to A5renova. Larger or more complex projects take longer.
Why do office fit out budgets go over?+
Usually because the quote left items out of scope, such as approval fees, furniture, AV or project management, or because materials were not named by brand, grade and thickness. Both come back as variations once you are committed.